RENOVATION BUDGET BREAKDOWN
TOTAL 2020 RENOVATION GOAL: ≈ $237K
Phase 1 (pre-April 5 goals) - $52k
Basement Kitchen, Classrooms & Bathrooms - $24k
Sanctuary ~ $30k
- paint (4k)
- flooring (8k)
- windows and plaster (8k)
- A/V system (8k)
Phase 2 (Spring goals) - $50k
Paint entire exterior - $30k
Furnace (16k) + tank removal (4k) ~ $20k
Phase 3 (Summer goals) - $30-35k
Roof - $30-35k
- repair/replace California gutter system with new gutters
- build flashing for backside of bell tower
- replace bell tower roofing/roof
- replace at least 1 more section of roof
Phase 4 (Fall goals) - $60-70k
Main floor ADA bathroom $60-70k
TBD ~ $30k
ADA Accessibility ramp/lift - $10k?
Downstairs office space - $8k
Electrical Service upgrade - $3-5k
A/C - $8k
If you have any questions or would like specific details on our financial status, please contact our church office at office@gracecityportland.org. All gifts are income tax deductible, as defined by the Internal Revenue Code for 501(c)(3) organizations.
Mailing Address: Grace City Portland, PO Box 83508, Portland, OR 97283